This page is intended to keep you informed of the progress we are making in the construction of our new high school. Should you have any questions please feel free to contact Community Relations Director John Thomas at Thomas@edgewood.k12.oh.us or call 863-4692 ext 1011.
Partners of Edgewood in the building project:
- Architect-Steed, Hammond and Paul
- Construction Manager-Quandel Construction
- State of Ohio Schools Facilities Commission
- Financing - Fifth Third Securities
- Bond Council - Peck, Shaffer & Williams LLP
- Land Surveyor-Bayer and Becker
- Commisioning Agents-Stan
- Geothermal - Jackson & Sons Drilling
- Landscaping - Evans Landscaping
- General Trades - Tri-Con Inc
- Masonry - Miter Masonry
- Roofing - M & W Metals Inc
- Casework - Farnham Equipment
- Kitchen Equip - Stafford Smith
- Fire Protection - Emerald Fire Protection
- Plumbing - Ken Neyer
- HVAC - Artic Heating & Air
- Electric - Reddy Electric
Location of new building-3045 Busenbark Road-what is now known as the Riner Farm
Timelines for building the new high school:
February 2009-passage of the bond Issue
Tuesday, March 24, 2009- community forum to begin the exterior design phase. Edgewood High School Cafeteria 6 pm.
March/April/May 2009 continue design phase including interior design with input from staff, administration and
community.
September/October 2009 complete all testing requirements and begin to set the foot print for the new building.
January 2010-send out bids for project
February/March 2010 award bids
April/May 2010 begin construction
June/July 2012 complete construction
August 2012 move in
Groundbreaking Ceremony September 20, 2009